The Port of Ferrol has achieved a significant milestone in offshore wind infrastructure logistics with its first XXL monopile handling operation. This complex operation demonstrates the port’s strategic role in the offshore wind industry and its advanced heavy-lift capabilities.
Project Specifications
Operation Details:
- Total Units: 10 monopiles
- Vessel Movements: 3 incoming, 4 outgoing
- Destination: Ronne, Denmark
- Timeline: Through July
- Maximum Unit Length: 86 meters
- Maximum Unit Weight: 2,100 tonnes
Operational Parameters
| Component | Specification | Notes |
|---|---|---|
| Monopile Length | 86m | Maximum |
| Unit Weight | 2,100t | Per piece |
| Vessel Calls | 7 total | 3 in, 4 out |
| Operation Window | 3 months | Until July |
| Planning Period | 1 month | Pre-operation |
Stakeholder Coordination
| Entity | Role | Responsibility |
|---|---|---|
| Port Authority | Coordination | Overall management |
| Navantia | Technical support | Engineering |
| Noatum Logistics | Logistics | Cargo handling |
| Mammoet | Heavy lift | Specialized equipment |
| Maritime Services | Port operations | Vessel support |






Energy Planning, We deliver breaking news, expert analysis, and actionable insights on: Renewable Energy Integration – Solar, wind, and storage breakthroughs; Grid Modernization – Smart technologies and infrastructure updates; Climate Policy – COP28 outcomes, carbon markets, and regulatory shifts; Emerging Tech – Hydrogen, CCUS, and AI-driven energy solutions
Our Partners: FR2 Infrastructure | We Simplify Complexity | Felipe Ramirez | Construction Methodology | Selknam | Energy Planning | Staging Diagrams
Discover more from Energy Planning
Subscribe to get the latest posts sent to your email.