Comprehensive analysis of wind turbine installation processes, focusing on production rates, critical lifts, and sequential assembly operations. Based on standard 4.5-6.0MW onshore turbines.
Component Specifications
Component Weight (t) Height/Length (m) Crane Requirement Foundation 600-800 20-25 (dia) 150t crawler Tower Sections 70-90 each 20-30 each 600t crawler Nacelle 80-100 12-15 600t crawler Hub 35-45 4-6 600t crawler Blades (each) 15-20 65-75 600t crawler
Installation Sequence Production Rates
FOUNDATION WORKS
Activity Duration (days) Team Size Equipment Excavation 2-3 6-8 Excavators Reinforcement 3-4 8-10 Mobile Crane Concrete Pour 1-2 10-12 Concrete Pumps Curing 7-14 – Monitoring
TOWER INSTALLATION
Section Duration (hrs) Team Size Wind Limit (m/s) Base 4-6 8-10 12 Mid 4-6 8-10 10 Top 6-8 8-10 8
NACELLE AND ROTOR
Component Duration (hrs) Team Size Wind Limit (m/s) Nacelle 6-8 10-12 8 Hub 4-6 8-10 8 Blades 8-12 10-12 6
Project Timeline (Single Turbine)
Phase Working Days Dependencies Site Prep 5-7 Weather/Access Foundation 15-20 Concrete Supply Hardstand 3-4 Ground Conditions Assembly 4-6 Wind Conditions Commissioning 3-4 Grid Connection
International Production Examples
EUROPEAN PROJECTS
Location Turbines Rate (units/month) Contractor Year UK 45 6-8 Vestas 2023 Germany 60 8-10 Siemens 2022 Spain 35 5-7 Nordex 2023 France 50 7-9 GE 2022
ASIA-PACIFIC PROJECTS
Location Turbines Rate (units/month) Contractor Year Australia 40 5-7 Vestas 2023 China 80 10-12 Goldwind 2022 India 55 7-9 Suzlon 2023 Japan 30 4-6 MHI 2022
Wind Turbine Crane Requirements and Assembly Analysis
Main Crane Specifications
PRIMARY LIFTING CRANE
Crane Type Capacity (t) Boom Length (m) Configuration Wind Limit (m/s) Liebherr LR1600 600 140-160 Main Boom + Luffer 8-10 Liebherr LG1750 750 140-160 Main Boom + Fixed Jib 8-10 Demag CC3800 650 140-160 Main Boom + Superlift 8-10 Manitowoc 18000 750 140-160 Main Boom + Fixed Jib 8-10
SUPPORT CRANE REQUIREMENTS
Purpose Capacity (t) Type Quantity Tailing Crane 200-250 All Terrain 1 Assembly Crane 100-150 Mobile 1 Components 80-100 All Terrain 1 Rigging Support 50-80 Mobile 1
Crane Assembly Sequence
MAIN CRANE SETUP
Activity Duration (hrs) Team Size Equipment Hardstand Prep 8-10 6-8 Dozers/Compactors Crane Platform 4-6 4-6 Support Crane Crawler Assembly 6-8 8-10 Support Crane Boom Assembly 8-10 8-10 Support Crane Superlift Setup 4-6 6-8 Support Crane
Component Lifting Analysis
TOWER SECTIONS
Section Weight (t) Height (m) Radius (m) Duration (hrs) Base 80-90 20-25 22-25 4-5 Mid 70-80 25-30 24-27 4-5 Top 60-70 30-35 26-29 5-6
NACELLE AND ROTOR
Component Weight (t) Radius (m) Height (m) Duration (hrs) Nacelle 85-95 28-32 120-140 6-8 Hub 35-45 30-34 120-140 4-6 Single Blade 15-20 35-40 120-140 3-4 each
Crane Pad Requirements
SPECIFICATIONS
Parameter Requirement Testing Method Ground Bearing 260-300 kPa Plate Load Test Platform Size 40m × 40m Survey Control Levelness ±25mm Laser Level Compaction 98% MDD Nuclear Density
Weather Limitations
OPERATIONAL LIMITS
Operation Max Wind (m/s) Visibility (m) Temperature (°C) Crane Assembly 12 >50 -10 to +35 Tower Sections 10 >100 -10 to +35 Nacelle Lift 8 >200 -10 to +35 Blade Install 6 >500 -10 to +35