Wind Turbine Installation Analysis – Production Rates and Methodologies

Comprehensive analysis of wind turbine installation processes, focusing on production rates, critical lifts, and sequential assembly operations. Based on standard 4.5-6.0MW onshore turbines.

Component Specifications

ComponentWeight (t)Height/Length (m)Crane Requirement
Foundation600-80020-25 (dia)150t crawler
Tower Sections70-90 each20-30 each600t crawler
Nacelle80-10012-15600t crawler
Hub35-454-6600t crawler
Blades (each)15-2065-75600t crawler

Installation Sequence Production Rates

FOUNDATION WORKS

ActivityDuration (days)Team SizeEquipment
Excavation2-36-8Excavators
Reinforcement3-48-10Mobile Crane
Concrete Pour1-210-12Concrete Pumps
Curing7-14Monitoring

TOWER INSTALLATION

SectionDuration (hrs)Team SizeWind Limit (m/s)
Base4-68-1012
Mid4-68-1010
Top6-88-108

NACELLE AND ROTOR

ComponentDuration (hrs)Team SizeWind Limit (m/s)
Nacelle6-810-128
Hub4-68-108
Blades8-1210-126

Project Timeline (Single Turbine)

PhaseWorking DaysDependencies
Site Prep5-7Weather/Access
Foundation15-20Concrete Supply
Hardstand3-4Ground Conditions
Assembly4-6Wind Conditions
Commissioning3-4Grid Connection

International Production Examples

EUROPEAN PROJECTS

LocationTurbinesRate (units/month)ContractorYear
UK456-8Vestas2023
Germany608-10Siemens2022
Spain355-7Nordex2023
France507-9GE2022

ASIA-PACIFIC PROJECTS

LocationTurbinesRate (units/month)ContractorYear
Australia405-7Vestas2023
China8010-12Goldwind2022
India557-9Suzlon2023
Japan304-6MHI2022

Wind Turbine Crane Requirements and Assembly Analysis

Main Crane Specifications

PRIMARY LIFTING CRANE

Crane TypeCapacity (t)Boom Length (m)ConfigurationWind Limit (m/s)
Liebherr LR1600600140-160Main Boom + Luffer8-10
Liebherr LG1750750140-160Main Boom + Fixed Jib8-10
Demag CC3800650140-160Main Boom + Superlift8-10
Manitowoc 18000750140-160Main Boom + Fixed Jib8-10

SUPPORT CRANE REQUIREMENTS

PurposeCapacity (t)TypeQuantity
Tailing Crane200-250All Terrain1
Assembly Crane100-150Mobile1
Components80-100All Terrain1
Rigging Support50-80Mobile1

Crane Assembly Sequence

MAIN CRANE SETUP

ActivityDuration (hrs)Team SizeEquipment
Hardstand Prep8-106-8Dozers/Compactors
Crane Platform4-64-6Support Crane
Crawler Assembly6-88-10Support Crane
Boom Assembly8-108-10Support Crane
Superlift Setup4-66-8Support Crane

Component Lifting Analysis

TOWER SECTIONS

SectionWeight (t)Height (m)Radius (m)Duration (hrs)
Base80-9020-2522-254-5
Mid70-8025-3024-274-5
Top60-7030-3526-295-6

NACELLE AND ROTOR

ComponentWeight (t)Radius (m)Height (m)Duration (hrs)
Nacelle85-9528-32120-1406-8
Hub35-4530-34120-1404-6
Single Blade15-2035-40120-1403-4 each

Crane Pad Requirements

SPECIFICATIONS

ParameterRequirementTesting Method
Ground Bearing260-300 kPaPlate Load Test
Platform Size40m × 40mSurvey Control
Levelness±25mmLaser Level
Compaction98% MDDNuclear Density

Weather Limitations

OPERATIONAL LIMITS

OperationMax Wind (m/s)Visibility (m)Temperature (°C)
Crane Assembly12>50-10 to +35
Tower Sections10>100-10 to +35
Nacelle Lift8>200-10 to +35
Blade Install6>500-10 to +35