Tidal/Wave Energy Plants Production Rate Analysis

Tidal and Wave Energy Plants represent complex marine renewable energy systems requiring specialized equipment, extensive environmental considerations, and precise installation timing. Production rates vary significantly based on resource availability, technology selection, and site conditions. Development timelines typically span 3-7 years from initial planning to commissioning, with critical procurement paths for specialized components.

Long Lead Items Analysis

ComponentLead TimeManufacturing ComplexitySupply Chain RiskCritical Specifications
Turbine System18-24 monthsExtremely HighCriticalSite-specific design
Generator Units14-18 monthsHighHighMarine certification
Foundation Systems12-16 monthsHighHighSeabed conditions
Power Take-off16-20 monthsHighCriticalPerformance specs
Control Systems12-14 monthsHighMediumMarine grade
Submarine Cables14-18 monthsHighHighMarine rating
Mooring Systems10-14 monthsHighMediumEnvironmental loads
Grid Connection16-20 monthsHighMediumInterface requirements

International Project Examples

Project NameCountryCapacity (MW)TechnologyConstruction PeriodProduction RateKey Features
MeyGenScotland398Tidal Stream2015-202185% availabilityMultiple turbines
Sihwa LakeSouth Korea254Tidal Barrage2004-201190% availabilityWorld’s largest
La RanceFrance240Tidal Barrage1961-196695% availabilityOldest operating
Nova InnovationScotland0.3Tidal Array2016-201980% availabilityCommercial array
MutrikuSpain0.3Wave Energy2006-201175% availabilityBreakwater integration
CETO 6Australia1.5Wave Energy2018-202170% availabilitySubmerged system
Orbital O2Scotland2Floating Tidal2019-202185% availabilityFloating platform
Swansea BayUK320Tidal Lagoon2022-2026Planned 90%Under development
Wave HubUK48Wave Test Site2010-2014Test facilityResearch facility
PenghuTaiwan0.5Tidal Stream2020-202275% availabilityTropical conditions
Bay of FundyCanada9Tidal Stream2018-202182% availabilityHigh tidal range
Raz BlanchardFrance14Tidal Stream2021-2024Planned 85%Array project
WestwaveIreland5Wave Energy2019-202270% availabilityTest facility
NagasakiJapan2Tidal Stream2019-202180% availabilityIsland location
Cook InletUSA5Tidal Stream2022-2025Planned 80%Arctic conditions

Critical Path Analysis

Major Risk Categories

Risk CategoryProbabilityImpactMitigation Strategies
Weather WindowsHighCriticalDetailed planning
Marine OperationsHighCriticalVessel availability
Environmental PermitsHighHighEarly engagement
Equipment DeliveryMediumHighBuffer scheduling
Grid ConnectionMediumHighEarly coordination
Seabed ConditionsHighCriticalDetailed surveys
Installation DelaysHighHighWeather contingency

Procurement Strategy

Critical Equipment

Equipment TypeProcurement Lead TimeKey ConsiderationsSupply Chain Risk
Turbines18-24 monthsCustom designLimited suppliers
Generators14-18 monthsMarine certificationMedium availability
Foundations12-16 monthsSite-specificFabrication capacity
Cables14-18 monthsTesting requirementsLimited suppliers
Control Systems12-14 monthsIntegration needsMedium availability
Installation Vessels12-18 monthsAvailabilityHigh demand

Country-Specific Requirements

United Kingdom

PhaseDurationRequirementsAuthorities
Scoping6-12 monthsEIA scopingMarine Scotland
Consenting12-24 monthsMarine licenseMMO/Marine Scotland
Grid Connection18-24 monthsConnection agreementNational Grid
Installation6-12 monthsMarine operationsMCA/Trinity House

France

PhaseDurationRequirementsAuthorities
Environmental Study12-18 monthsImpact assessmentMinistry of Environment
Maritime Consent12-24 monthsMaritime authorizationMaritime Prefecture
Grid Connection18-24 monthsConnection agreementRTE
Installation Permit6-12 monthsConstruction permitRegional Authority

Canada

PhaseDurationRequirementsAuthorities
Environmental Assessment12-24 monthsFederal/Provincial EACEAA/Provincial
Marine Permit12-18 monthsMarine licenseDFO
Grid Connection18-24 monthsConnection agreementProvincial Utility
Installation6-12 monthsMarine operationsTransport Canada

Production Rate Factors

Technical Factors

  1. Resource Characteristics
    • Tidal range/current speed
    • Wave height/period
    • Site conditions
  2. System Design
    • Technology type
    • Rated capacity
    • Operating parameters
  3. Environmental Conditions
    • Weather windows
    • Marine conditions
    • Seasonal variations

Construction Elements

ElementDurationDependenciesCritical Considerations
Onshore Infrastructure6-12 monthsPermitsAccess requirements
Foundation Installation3-6 monthsWeather windowsMarine conditions
Device Installation3-6 monthsFoundation completionVessel availability
Cable Installation2-4 monthsRoute preparationWeather conditions
Grid Connection3-6 monthsCable installationTesting requirements
Commissioning2-4 monthsSystem completionPerformance validation

Installation Vessels

Vessel TypeLead TimeAvailabilityCost Impact
Heavy Lift12-18 monthsLimitedHigh
Cable Lay12-16 monthsLimitedHigh
Support Vessels6-12 monthsMediumMedium
Survey Vessels3-6 monthsGoodLow
Crew Transfer3-6 monthsGoodLow