Tidal and Wave Energy Plants represent emerging renewable technologies that harness ocean energy . These facilities face unique challenges due to their marine environment, requiring specialized materials, robust construction methods, and complex installation procedures. Construction typically spans 24-48 months, with critical components requiring procurement initiation 18-24 months before installation.
Primary Long Lead Items Analysis Table
Component Lead Time Manufacturing Complexity Supply Chain Risk Critical Specifications Turbine Systems 16-24 months Extremely High Critical Marine environment Wave Energy Converters 18-24 months High Critical Survivability rating Foundation Systems 14-18 months High High Seabed conditions Submarine Cables 12-18 months High High Marine certification Power Take-off Systems 14-20 months High Critical Reliability specs Control Systems 12-16 months High Medium Remote operation Grid Connection 16-20 months High Medium Subsea requirements Monitoring Systems 10-14 months High Medium Environmental resistance Mooring Systems 12-16 months High High Storm survival Installation Vessels 18-24 months Critical High Specialized equipment
Project Name Country Capacity (MW) Technology Type Construction PeriodKey Features Major Challenges MeyGen Scotland 398 Tidal Stream 2015-2021 Largest tidal array Strong currents Sihwa Lake South Korea 254 Tidal Barrage 2004-2011 World’s largest Environmental impact La Rance France 240 Tidal Barrage 1961-1966 First large-scale Pioneer technology Nova Innovation Scotland 0.3 Tidal Array 2016-2019 Commercial array Grid integration Mutriku Spain 0.3 Wave Energy 2006-2011 Breakwater integration Storm survival CETO 6 Australia 1.5 Wave Energy 2018-2021 Submerged system Marine conditions Orbital O2 Scotland 2 Floating Tidal 2019-2021 Floating platform Installation challenges Swansea Bay UK 320 Tidal Lagoon 2022-2026 Planned project Planning approvalWave Hub UK 48 Wave Test Site 2010-2014 Test facility Technology testing Penghu Taiwan 0.5 Tidal Stream 2020-2022 Tropical conditions Typhoon resistance Bay of Fundy Canada 9 Tidal Stream 2018-2021 High tidal range Extreme currents Raz Blanchard France 14 Tidal Stream 2021-2024 Array project Complex installation Westwave Ireland 5 Wave Energy 2019-2022 Test facility Atlantic conditions Nagasaki Japan 2 Tidal Stream 2019-2021 Island location Typhoon protection Cook Inlet USA 5 Tidal Stream 2022-2025 Arctic conditions Ice management
Critical Path Risk Analysis
Technical Risks
Risk Category Probability Impact Mitigation Strategies Marine Environment High Critical Material selection Weather Conditions High Critical Design redundancy Installation High High Weather windows Grid Connection Medium High Redundant systems Equipment Reliability High Critical Robust design
Phase Risk Level Key Concerns Control Measures Site Assessment High Seabed conditions Detailed surveys Foundation Installation Critical Weather windows Vessel availability Device Installation Critical Marine operations Installation planning Cable Installation High Seabed protection Route engineering Commissioning High System integration Phased testing
Project Timeline Critical Elements
Site Development
Resource assessment
Environmental studies
Seabed surveys
Grid connection planning
Engineering
Device optimization
Foundation design
Installation planning
Operations strategy
Procurement Strategy
Vessel contracts
Equipment orders
Installation tools
Weather forecasting
Activity Duration Dependencies Critical Factors Site Preparation 6-12 months Weather windows Marine conditions Foundation Installation 6-12 months Vessel availability Weather windows Device Installation 6-18 months Foundation completion Marine operations Cable Installation 3-6 months Route clearance Weather conditions Commissioning 3-6 months Grid connection System testing
Risk Mitigation Recommendations
Marine Operations
Weather forecasting
Vessel selection
Installation methods
Contingency planning
Quality Management
Material certification
Installation procedures
Testing protocols
Documentation
Environmental Management
Impact assessment
Monitoring systems
Marine life protection
Sediment control
Success Factors
Technical Excellence
Device Performance
Reliability design
Maintenance access
Monitoring systems
Performance optimization
Installation Management
Vessel coordination
Weather planning
Safety systems
Quality control
Operational Strategy
Maintenance planning
Remote monitoring
Emergency response
Performance analysis
Environmental Considerations
Key Areas
Marine Environment
Habitat protection
Sediment management
Noise control
Visual impact
Operational Impact
Marine life monitoring
Sediment transport
Water quality
Ecosystem effects
Safety Systems
Critical Elements
Marine Operations
Vessel procedures
Personnel safety
Emergency response
Weather monitoring
Maintenance Operations
Access systems
Safety equipment
Communication systems
Emergency protocols
Like this: Like Loading...