Situated in Laguna Province, the Kalayaan 2 Project will be equipped with 17 GW165-6.0MW wind turbines. Goldwind is responsible for the equipment supply, transportation, installation, and commissioning, and a ten-year comprehensive operation and maintenance service for the project. TBC, the project owner, operates as a multinational power corporation with business in countries including Singapore, Vietnam, Thailand, and Cambodia. It is dedicated to promoting renewable energy development in ASEAN nations. The partnership with Goldwind is expected to yield mutual benefits as both parties strive to propel the energy transition.

March Progress Highlights

✔ First Wind Turbine Generator foundation completed – Concrete pouring finalized
✔ Initial WTG components successfully received & offloaded at Batangas Port

Project Impact

  • Expanding renewable energy infrastructure in the Philippines
  • Strengthening the country’s clean energy transition

Collaboration & Partnerships

Working alongside:
✓ ACCIONA Energía
✓ Bureau Veritas Group
✓ Goldwind

Special recognition to the dedicated project team driving progress.


More Info


Discover more from Energy Planning

Subscribe to get the latest posts sent to your email.

By Energy Planning

Energy Planning, We deliver breaking news, expert analysis, and actionable insights on:  Renewable Energy Integration – Solar, wind, and storage breakthroughs; Grid Modernization – Smart technologies and infrastructure updates; Climate Policy – COP28 outcomes, carbon markets, and regulatory shifts;  Emerging Tech – Hydrogen, CCUS, and AI-driven energy solutions Our Partners: FR2 Infrastructure | We Simplify Complexity | Felipe Ramirez | Construction Methodology | Selknam | Energy Planning | Staging Diagrams

Leave a Reply

Discover more from Energy Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading