Project Milestones Achieved
Buronga Substation
- All mechanical and electrical works completed
- Now focused on final testing and commissioning
- Key construction stats:
✓ 24,000m³ of concrete poured
✓ 1,800 concrete piles installed
✓ 420,000m of low-voltage cable laid
Wagga Wagga Substation
- Civil, electrical, and structural works completed
- Next phase: Testing and commissioning to connect to EnergyConnect transmission lines
Project Significance
- Part of EnergyConnect, Australia’s largest electricity transmission project
- Will enable:
✓ Greater access to renewable energy
✓ Improved grid reliability and security
✓ Enhanced interstate energy connections

Energy Planning, We deliver breaking news, expert analysis, and actionable insights on: Renewable Energy Integration – Solar, wind, and storage breakthroughs; Grid Modernization – Smart technologies and infrastructure updates; Climate Policy – COP28 outcomes, carbon markets, and regulatory shifts; Emerging Tech – Hydrogen, CCUS, and AI-driven energy solutions
Our Partners: FR2 Infrastructure | We Simplify Complexity | Felipe Ramirez | Construction Methodology | Selknam | Energy Planning | Staging Diagrams
Discover more from Energy Planning
Subscribe to get the latest posts sent to your email.