One step closer to finalising the construction of Blyth Battery for Neoen Australia!
The last battery packs are arriving on-site, and colleagues from NHOA Energy are starting to pre-commission them to allow for ramp-up of the facility in the coming months.

Some fast facts about the project:
⚈ 345 days since Elecnor entered the site.
⚆ Elecnor has collaborated with over 50 different companies during the construction.
⚈ Almost 150 people working on site at the same time at the peak of construction.
⚆ 64 inverters &1060 batteries have been installed.


Discover more from Energy Planning

Subscribe to get the latest posts sent to your email.

By Energy Planning

Energy Planning, We deliver breaking news, expert analysis, and actionable insights on:  Renewable Energy Integration – Solar, wind, and storage breakthroughs; Grid Modernization – Smart technologies and infrastructure updates; Climate Policy – COP28 outcomes, carbon markets, and regulatory shifts;  Emerging Tech – Hydrogen, CCUS, and AI-driven energy solutions Our Partners: FR2 Infrastructure | We Simplify Complexity | Felipe Ramirez | Construction Methodology | Selknam | Energy Planning | Staging Diagrams

Leave a Reply

Discover more from Energy Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading